  • All civil services are in place.
  • Blocks 1 and 3’s roofs are 80% completed and have received their first coats of paint.
  • Block 2’s roof has been completed and has received its first coat of paint.
  • Boundary wall has been erected and is awaiting finishing touches.
  • The Construction team has started with the foundations of the Care Centre.
  • The Clubhouse’s roof has been completed and is receiving its first (external) and final (internal) coat of paint.